Customer: BrisConnections
Construction Sector: Infrastructure
- The $4.8 billion Airport Link, Northern Busway and Airport Roundabout Upgrade projects were Australia's largest road infrastructure project.
- Hanson was responsible for supplying 2,900m3 of concrete in a continous pour for the project- the largest single pour ever completed by Hanson in South East Queensland
- Specifically developed and trialled for the project Hanson supplied a low heat mix
- The pour was completed in 10 hours
- It required 64 agitators, 5 concrete plants (decreasing to 4) and 31 pre-loaded tippers.
- Not one of the 424 loads batched and delivered to site was rejected